Historic Willimansett Bridge Rehabilitation

 
 
hero graphic
Northern Construction Yellow Truck

Historic Willimansett Bridge Rehabilitation

Industry: Bridge & Highway Rehabilitation
Start Date: May 12, 2014
Completion Date: July 1, 2015

Massachusetts Route 116 crosses the Connecticut River between Chicopee and Holyoke via the historic Willmansett Bridge. It provides an important regional transportation link for local motorists and pedestrians.

The Massachusetts Department of Transportation (MassDOT) initiated a comprehensive bridge rehabilitation that aimed to extend the bridge’s service life, eliminate load restrictions and improve safety. Nearby communities and businesses would be affected by the bridge’s extended closure, so restoring access as quickly as possible became a major priority. Northern Construction completed the project ahead of schedule by carefully coordinating scheduling, construction and field solutions. Here’s how the process worked.

The Scope of Our Work

The historic Willimansett Bridge spans approximately 793 feet across the Connecticut River. It includes four steel through-trusses measuring approximately 170 feet each. Two approximately 51-foot steel girder approach spans connect the body of the bridge to the roadways. Originally built in 1891, the bridge is identifiable by its distinctive four-truss design.

The bridge has undergone multiple improvements and updates throughout its long service life. This particular rehabilitation project would involve the strengthening, repair or replacement of numerous structural components, including the:

  • Bridge deck
  • Truss lower chords and gusset plates
  • Stringers and floor beams
  • Bracing members
  • Sidewalk brackets
  • Bridge bearings
  • Truss top chords and diagonals
  • Crash-tested curb and pedestrian railings
  • Steel girder approach spans

Additional work was also needed, including:

  • Masonry repairs to existing piers, abutments and wingwalls
  • Reventment
  • Roadway safety improvements
  • Utility installation and relocation
  • Highway lighting updates and associated side work.

The primary challenge with the project was that the original contractor defaulted after the road was already closed to traffic, running the risk of substantial delays while the bonding company searched for a new contractor. Northern Construction stepped in and moved quickly. Efficiency was a core driver as we got started.

Unique Project Challenges and Solutions​

Recovering a Project Following Contractor Default

The departure of the bridge project’s existing contractor created added inconveniences for the drivers and pedestrians who rely on the Willimansett Bridge. Northern Construction began work with the goal of minimizing the duration of the closure. 

By closely coordinating with stakeholders like MassDOT, Benesch, subcontractors and field personnel, we implemented a system that allowed multiple aspects of the project to proceed at once. These included:

  • Structural steel repairs
  • Bridge deck construction
  • Utility work
  • Painting

We also carefully coordinated manpower and bandwidth to optimize processes. Where necessary, crews worked extended days and double shifts to accelerate construction. However, the same rigorous safety and quality standards were applied throughout the process.

Preserving and Strengthening the Historic Structure

At the time of this project, the Willimansett Bridge was already more than 120 years old and a familiar landmark in the area. The rehabilitation project had to improve the bridge’s structural performance while maintaining its historic steel-truss configuration. In an effort to ensure we met both goals, we leveraged a couple of different engineering solutions:

  • A site-specific seismic assessment minimized the amount of seismic retrofit work required. This also helped maintain the integrity of the existing structure. 
  • Temporary post-tensioning was used to facilitate the complete replacement of the truss bottom chords.

By implementing these techniques, we were able to complete our work more efficiently and without unnecessary structural alterations.

Maintaining Pedestrian Access

The Willimansett Bridge was closed to vehicle traffic throughout the rehabilitation project, but pedestrian access had to remain available. To accommodate the compressed project timeline, we developed an updated pedestrian-access plan that added to our efficiency.

The original plan divided sidewalk construction into two phases, requiring one side of the bridge at a time to remain open to pedestrians. To streamline the process, we developed a crossover that guided pedestrians through an open portion of the bridge deck. We were able to construct both sidewalks during a single phase without sacrificing pedestrian or contractor access.

Painting Through the Winter

The bridge required new paint, but given the project’s timeline, much of this work needed to be completed in the winter. As a result, there were concerns that the colder temperatures could extend the timeline, delay completion and create negative conditions for optimal painting. 

We developed contingency plans that allowed us to maintain progress despite the season. Coating work was done under full containment using temporary heating. Besides creating the right conditions for painting, the processes supported the hazardous-materials controls necessary when working around lead paint on the existing structures.

Working Near River and Railroad

The Willimansett Bridge spans the Connecticut River and sits adjacent to the active Pioneer Valley Railroad. The construction area was somewhat constrained, and we had to adopt various techniques to avoid overly disturbing the area or interrupting normal rail operations. 

The work involved excavation support, utility relocations, environmental permitting and limited access around the existing structure. As part of the process, we developed detailed staging plans and coordinated carefully among bridge crews, railroad stakeholders, utility personnel and environmental specialists. Regarding the railroad specifically, we used a slide-rail shoring system to support excavation near the railroad while minimizing vibration impacts.

Project Highlights & Takeaways

The greatest outcome of our Willimansett Bridge project was that we completed the project 30 days ahead of the promised schedule, despite the delays posed by the departure of the other contractor. Through careful planning, staging and adjustment of processes, we maintained the project’s workload and preserved pedestrian access while accelerating the overall schedule. 

As a result of the Route 116 bridge rehabilitation, Northern Construction received a 2016 Engineering Excellence Bronze Award from the American Council of Engineering Companies of Massachusetts. We remain committed to upholding this high standard of efficiency and excellence across all our projects.

target on line

WORKING TOGETHER WITH ENGINEERS

We partner closely with engineers to bring their designs to life. We’re pre-qualified with multiple agencies to create an efficient proposal process. 

Safety and accuracy are our top priorities. When you work with Northern Construction, you can trust that we pay close attention to every detailed specification and requirement. 

INDUSTRIES WE SERVE
 

SAFETY FIRST

We prioritize safety guidelines in our project planning  because we care about our clients, construction workers, and communities. Click the link below to see how we consistently exceed safety standards.